An Uncommon Aid Project
Schedule
Beginning
Appeal for donations 6 - 8 months
Project preparation 2 - 3 Monate
Inauguration
Moving in
Budget
Framing / masonry 4.400,- € Interior plastering       2.250,- € Exterior plaster, incl. skirting 1.750,- € Roof and insulation                9.000,- € Roofing tiles 2.000,- € Cabinetry / interior doors 1.500,- €
Windows 2.000,- € Floor coverings, stairs, veranda 1.350,- € Painting        1.000,- € Electrical      2.750,- € Plumbing       2.200,- € Expenses                                          2.800,- €
Total 33.100,- € (amounts are approximate based on initial estimate)
Realization of the project 5 - 6 months